CeD3 Project Updates - July 2014
Back to Project Updates
Reporting Period
24 June - 30 July 2014
Status Summary
The build of the Staging Database and layer one ETL is near completion. Dan is still working with Sydney, Townsville and Canberra Goulburn offices as trials for the data schema and build design. Canberra-Goulburn staging has been reviewed and close completion
Work is continuing on the data mart design and build and ETL for layer two.
Bradley (Brad) Dixon commenced at CEnet on 14 July and has been focused on “getting up to speed”.
Some initial discussions have been held with a couple of dioceses to assist with CED3 preparation.
This Reporting Period
Reporting Period
24 June - 30 July 2014
Status Summary
The build of the Staging Database and layer one ETL is near completion. Dan is still working with Sydney, Townsville and Canberra Goulburn offices as trials for the data schema and build design. Canberra-Goulburn staging has been reviewed and close completion
Work is continuing on the data mart design and build and ETL for layer two.
Bradley (Brad) Dixon commenced at CEnet on 14 July and has been focused on “getting up to speed”.
Some initial discussions have been held with a couple of dioceses to assist with CED3 preparation.
This Reporting Period
Corrective Actions Undertaken
The issues with the provision of the required data from Sydney has been addressed and Dan will now complete the work and hand over to Sydney DBA.
Next Reporting Period
The next period will see:
Products to be completed
The issues with the provision of the required data from Sydney has been addressed and Dan will now complete the work and hand over to Sydney DBA.
Next Reporting Period
The next period will see:
- finalising the design and build of the staging database,
- completion of the first ETL layer, and
- the completion of testing using data from Sydney and Canberra-Goulburn
- Testing ETL with Townsville,
- Visit to BCE - Brad, Dan and Ian,
- Mapping of the reports for delivery.
Products to be completed
Corrective Actions
Nil
Project and Stage Tolerance Status
The project is well within budget.
The completion date for delivery has been set back by 4-6 weeks to mid Term Four 2014.
Requests for Change
Nil
Key Issues and Risks
(Summary of actual or potential problems and risks)
The success of the CG staging means data will be in the staging and the next layer of work can be attempted. This has reduced the impact of the recently identified risks to the timeline arising from the slowness with Sydney.
Lessons Report (if appropriate)
(A review of what went well, what went badly, and any recommendations for corporate or programme management consideration)
Nil
Nil
Project and Stage Tolerance Status
The project is well within budget.
The completion date for delivery has been set back by 4-6 weeks to mid Term Four 2014.
Requests for Change
Nil
Key Issues and Risks
(Summary of actual or potential problems and risks)
The success of the CG staging means data will be in the staging and the next layer of work can be attempted. This has reduced the impact of the recently identified risks to the timeline arising from the slowness with Sydney.
Lessons Report (if appropriate)
(A review of what went well, what went badly, and any recommendations for corporate or programme management consideration)
Nil